What a General Contractor Should Expect in a Division 26 Scope Letter

The eight things a Division 26 electrical scope letter should contain so your low bid is defensible and your change-order log stays short.

If you run projects for a general contractor, you read a lot of electrical proposals. Most of them are a lump-sum number, a paragraph of boilerplate and a list of exclusions long enough to make you nervous. The scope letter that actually protects you on bid day looks different. Here is what Steel City Electric puts in ours, and what you should expect from any Division 26 subcontractor bidding your work in Bradenton, Sarasota or Tampa Bay.

1. A line-by-line response to your spec, not a summary of it

The scope letter should walk the Division 26 (and 27/28 if we are carrying them) sections in order and say what is included for each: service and distribution, feeders and branch, lighting and controls, fire alarm or low-voltage pathways, temporary power, testing, closeout. When a section is excluded or carried by another trade, it should say so in that section, not buried at the end. If you can lay the letter next to the spec table of contents and check them off, it is doing its job.

2. The service and utility assumptions, stated plainly

Service size and voltage (for example, 1,200 A at 480Y/277V three-phase), the utility we assumed (FPL, Duke Energy, TECO or Peace River), whether the transformer pad, primary conduit and metering are in our scope or the utility’s, and whether utility fees are included or passed through. This is where most electrical change orders are born. A good letter also notes anything we saw on the site walk that could move the number, such as an undersized existing service or a long primary run.

3. Named equipment, not “or equal” everywhere

Switchgear and panelboard manufacturer, generator and ATS manufacturer, lighting-control platform. If we are proposing an alternate to the spec basis of design, the letter names it and prices the difference separately. That lets you compare bids honestly and keeps the owner’s engineer from rejecting the submittal in week three.

4. Clarifications and exclusions that are specific

“Excludes anything not shown” is not a clarification. Specific clarifications read like: “Excludes patching and painting of existing finishes,” “Includes two mobilizations for the underground; additional mobilizations billed at $X,” “Permit fees included; impact fees excluded,” “Owner-furnished fixtures installed per the schedule dated 9/12.” Each one is a conversation you are not having mid-project.

5. Alternates and value engineering, priced

If there is a real way to lower cost without lowering quality, the letter should offer it as a priced alternate: a different lighting-control approach, aluminum feeders where the spec allows, a generator one size down with a load calculation to back it. You should never have to ask “is there anything we can do on price?” and get a vague answer.

6. Schedule and manpower commitments

How many weeks for rough-in, when switchgear needs to be released to hit the energization date, and what crew size we are planning. On a tight schedule we also include the long-lead dates we need from you: when the pad has to be ready for the utility, when the electrical room needs to be dried in.

7. Proof of license, bonding and insurance, attached

The letter should come with the state license number (ours is EC13014807), a certificate of insurance and bonding capacity so your owner has nothing to chase. If a sub cannot attach these on bid day, that tells you something.

8. The exact drawing set and addenda it is based on

Drawing set date, addenda acknowledged, and any RFIs we issued during bidding with the answer we assumed. When the set changes, you both know exactly what moved.

Why it matters

A scope letter is not a formality. It is the document the project manager, the owner and, if it goes badly, the lawyers will read. A clear one makes the low bid defensible and the change-order log short. It is step two of our 6-Step Program for every commercial project, and it is why general contractors across Manatee, Sarasota and Hillsborough counties keep sending us plans.

Have a set out for bid? Submit a bid invitation and we will return a scope letter that reads line by line with your spec. Steel City Electric is a Florida State Certified, fully bonded and insured commercial electrical contractor based in Bradenton, serving Sarasota, Lakewood Ranch and Tampa Bay.